Exercise 9.2A

This exercise relates to the listening passage on page 9.2. You can listen to the passage again here:

Note down, in English, what tasks were completed by each deadline. In each case click on 'show answer' to see if your response is correct.

10 April

plan of primary data collection

late April

sample form, interview questionnaire, advice for interviewers and observers

early May

formed research group, selected people who would carry out the fieldwork, data processing experts and people who would analyse and prepare the final report; guidelines for the group tasked with collecting primary data; duplication of materials for the pilot study

21 May

training session for interviewers, observers and others

2-3 June

pilot study in Kyiv over the weekend; showed that the programme and paperwork needed to be amended; duplication of corrected materials

September

main study, avoiding holiday period in July and August

October

collected data prepared for processing: checking, editing, encoding

mid-November

completion of computer analysis (a lengthy process, as there were almost 500 respondents)

at this time

analysis of results, preparation of draft report

shortly

presentation of initial findings and recommendations at the university